Parking Deck & Phase 2
Woodward HS Updates:
Parking Deck:
Schedule the elevator and complete the punch list.
Phase 2
Ground rough-ins are complete and compacted.
Masonry walls are in progress.
Area F waterproofing and backfilling are in progress.
Mechanical and electrical rough-ins are ongoing.
Preparing exterior floors for cold weather conditions.
Concession stand is awaiting the SOE permit, which is currently with MC.
Currently installing Walls 9, 2, 13, and 12.
Relocating Wall 2 disrupts the layout due to a manhole conflict.
Storm drain work will resume after the new year.
Working on Grading of the football field.