Parking Deck & Phase 2

Woodward HS Updates:

Parking Deck:

  • Schedule the elevator and complete the punch list.

Phase 2

  • Compacted, formed, and poured the bottom portion of the seating area for the auditorium.

  • Completed the masonry walls for the aux gym and outdoor storage room off the aux gym.

  • Building up masonry walls in the area G corridor to the aux gym.

  • Installing stone block walls 13, 12, and 1.

  • Roughing in underground electrical and mechanical in area F.

  • Fencing installed along walls 8, 9, 10, and 12.

  • Installed support of excavation at the North-West corner of the existing building for the building expansion.

  • Starting installation of the support of excavation at the concession stand and wall 15 area.

  • Grading the football area