Phase 1 Building, Parking Deck & Phase 2- Aux Gym

Woodward HS Updates:

Parking Deck:

  • Elevator incidentals ongoing, need to schedule inspection, roofers coming on oct 29th, a flooring crew is currently present.

Phase 2

  • Area G rough ins/backfill/CMU walls/stone continuing

  • Area F waterproofing/footings/walls/backfill/rough-ins continuing

  • Concession stand surveyors will be here Thursday to locate the duct bank.

  • Mixing soil with sand for wall backfill

  • Continuing walls 1/9/12, continuing install of the storm drains

  • Continuing rough-ins for greenhouse

  • Grandstand piers to be completed this week

Next
Next

Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field