Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field

Woodward HS Updates:

Parking Deck:

  • Elevator Going in and expected to be finished by 9/19/2025.

Phase 2

  • Got Elevations for both USG, will be working on bringing it up to grade

  • Continuing with wall / waterproofing / backfilling are G & F

  • Continuing CMU wall / footings

  • Continuing plumbing & electric rough-in

  • Upgraded grandstand footing plan - Footings start week of September 29th.

  • WSSC inspected & passed plumbing

Next
Next

(July 2025) Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field