(July 2025) Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field

Woodward HS Updates:

Parking Deck:

  • Installed the waterline that services the garage

  • Caulking of the pre-cast concrete and cast in place concrete for both the upper and lower level

  • Worked on getting the elevator shaft ready by installing the sump pump, lighting fixtures, and power

Phase 2

  • Continuing to reinforce, form, and pour footings in the building addition, heading north

  • Began waterproofing the retaining wall to allow for CMU foundations and backfill, continuing up the wall as CMU and backfill are added

  • Started the CMU foundations for the building addition

  • Completed the demolition of the temporary parking lot on the eastern side of the school

  • Excavated for UGS 1 where the temporary parking lot stood

  • Placed down the liner and stone that will envelop the structure

  • Began installing the UGS 1 structure