June 2025:

Phase 1:

  • Complete striping for tennis and pickleball courts

  • Installed the tennis court nets

Parking Deck:

  • Installed the fire pump in the water service room

  • The barrier cables along the ramp were installed

  • The stairways received paint on the railings

  • Treads for the stairs were installed

Phase 2:

  • Continuing to excavate and pour footings for the concrete retaining wall within the phase 2 building as well as for the aux gym

  • Starting to reinforce, form, and pour positions of the concrete retaining wall

  • The demolition of the temporary parking lot started on the eastern side of the school to proceed with the installation of UGS 1

  • Starting to fill in the retaining pond at the south-east side of the site