June 2025:
Phase 1:
Complete striping for tennis and pickleball courts
Installed the tennis court nets
Parking Deck:
Installed the fire pump in the water service room
The barrier cables along the ramp were installed
The stairways received paint on the railings
Treads for the stairs were installed
Phase 2:
Continuing to excavate and pour footings for the concrete retaining wall within the phase 2 building as well as for the aux gym
Starting to reinforce, form, and pour positions of the concrete retaining wall
The demolition of the temporary parking lot started on the eastern side of the school to proceed with the installation of UGS 1
Starting to fill in the retaining pond at the south-east side of the site