July 2025:
Parking Deck:
Installed the waterline that services the garage
Caulking of the pre-cast concrete and cast in place concrete for both the upper and lower level
Worked on getting the elevator shaft ready by installing the sump pump, lighting fixtures, and power
Phase 2:
Continuing to reinforce, form, and pour footings in the building addition, heading north
Began waterproofing the retaining wall to allow for CMU foundations and backfill, continuing up the wall as CMU and backfill are added
Started the CMU foundations for the building addition
Completed the demolition of the temporary parking lot on the eastern side of the school
Excavated for UGS 1 where the temporary parking lot stood
Placed down the liner and stone that will envelop the structure
Began installing the UGS 1 structure