Flooring continues, site work progresses, and metal panels are nearing completion!

  • Flooring continues to be placed from the third floor down to the ground floor, with the first floor now in progress.

  • Gym wood flooring has been placed, with the bleachers being delivered this week.

  • The ceiling grid continues, pushing the electrician and plumbers to finish their above ceiling work.

  • Our painter continues to chase our drywall contractor as he completes all his bulkhead work.

  • All metal lockers have been delivered and are currently being assembled.

  • Toilet partitions are being installed in bathrooms throughout the building.

  • Metal panels are wrapping around the front of the school.

  • The site contractor is currently setting the last two large storm water management systems in front of the school.

Previous
Previous

With Warm Weather on the Horizon, Finishes Heat Up!

Next
Next

Building Now Fully Enclosed!