Earthwork and Building Pad
The first milestone for sediment basins installation has been completed. The earthwork contractor is continuing earthwork efforts and is currently working on getting the new Woodward High School building pad on the subgrade. These efforts include grading of the soil, installing stormwater management structures, demolishing the existing building pad/foundation, preparing the soil for grading by removing left-over debris from the old school’s building pad, and installing pipes and storm structures on the job site.
You can find more progress photos here.