Progress Continues with Interior and Exterior Work!

  • Interior of Building

    • Ceiling tile being installed on the 3rd floor.

    • Flooring continues on 1st floor and ground floor.

    • Resinous flooring has been completed in all 4 main stair ways.

    • The gym floor has been lined and sealed.

    • Mirrors are being installed in the black box and dance rooms.

    • Elevator work has commenced.

  • Exterior of Building

    • Telecom communications duct bank complete running into the building.

    • Installation of the bio ponds at the front of the building has started.

    • Metal Panels are nearing completion with the south façade being the final area to finish.

    • Fencing along the block walls continues near the bus loop parking lot.

    • Site sidewalks around the exterior continue to be poured. 

Next
Next

Progress continues for both interior and exterior work.