With spring arriving, Woodward continues enclosure.

Sheathing wraps around the building as interior paint, windows, and utilities continue to progress.

  • Windows are now installed along the east gym wall and the adjacent stair tower. An echo can now be heard in these two rooms as they begin to become completely enclosed.

  • Brickwork increases in the courtyard.

  • The final pieces of steel have been laid over the southern loading dock as the final pieces of decking are placed.   

  • The roofer has one more section of roof to complete before our building will be entirely covered.

  • The southeastern and southwestern stair towers are nearing completion, with only one more staircase to go.