Structural Steel and Site Retaining Wall Construction Begins
Earthwork, concrete, masonry, and underground utilities are ongoing as the steel and site retaining walls work begins.
Poured concrete slab on grade at lower end of the building.
Currently pouring lower-level concrete foundations and concrete walls.
Currently building masonry walls for the gym, mechanical room, and stair tower.
Started erecting steel at the north end of the building, which broadly covers staff administration, storage, special education, and classrooms.
Started installing site retaining walls at the south end of the property.
Plumbing and electrical rough-ins are following our concrete foundations.