(MAY 2025) Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field

Woodward HS Updates:

Phase 1 Building

  • Complete installation of tennis court fencing

  • Install counter tops inside the greenhouse

  • Start striping for tennis and pickleball courts

Parking Deck:

  • Poured the last slab on grade portion of the lower level in the garage

  • Install light fixtures on the lower level

  • Install CMU wall on the lower level, underneath the ramp

  • Install CMU walls for the elevator machine room, water service room, and electric room on the lower level

  • Handrails for the two stairs were installed

Phase 2-Aux Gym, Auditorium, and Ball Fields

  • Excavate and pour footings for the concrete retaining wall within the phase 2 building