(MAY 2025) Phase 1 Building, Parking Deck & Phase 2- Aux Gym, Auditorium & Ball Field
Woodward HS Updates:
Phase 1 Building
Complete installation of tennis court fencing
Install counter tops inside the greenhouse
Start striping for tennis and pickleball courts
Parking Deck:
Poured the last slab on grade portion of the lower level in the garage
Install light fixtures on the lower level
Install CMU wall on the lower level, underneath the ramp
Install CMU walls for the elevator machine room, water service room, and electric room on the lower level
Handrails for the two stairs were installed
Phase 2-Aux Gym, Auditorium, and Ball Fields
Excavate and pour footings for the concrete retaining wall within the phase 2 building