Phase 2:

  • Aux gym joists and decking have been installed.

  • Steel supports for the gym equipment is installed and overhead mechanical, plumbing, and electrical rough ins are on going.

  • Currently working on pointing up the exterior of the block blocks at the aux gym.

  • Steel and decking are in place for the ground floor of area G.

  • Interior masonry for ground floor area G will be starting soon.

  • Area F steel for the set work shop and dressing rooms has been set.

  • Continuing to set steel in area F where the practice studio will be.

  • Continuing on foundation work at the front of the building.

  • Interior block walls inside the orchestra pit have been installed.

  • Football field has been graded and underground utilities installed.

  • Currently working on installing the perimeter trench drain for the field.

  • MUSCO stadium lights have been installed. 

  • Walls 1, 2, and 12 are complete.

  • Installing walls 13 and 15 currently. 

  • Concession stand concrete walls are installed.

  • Currently working on the remaining footings of the concession stand.

  • Continuing to run underground electric throughout the football stadium.