Phase 2:
Aux gym joists and decking have been installed.
Steel supports for the gym equipment is installed and overhead mechanical, plumbing, and electrical rough ins are on going.
Currently working on pointing up the exterior of the block blocks at the aux gym.
Steel and decking are in place for the ground floor of area G.
Interior masonry for ground floor area G will be starting soon.
Area F steel for the set work shop and dressing rooms has been set.
Continuing to set steel in area F where the practice studio will be.
Continuing on foundation work at the front of the building.
Interior block walls inside the orchestra pit have been installed.
Football field has been graded and underground utilities installed.
Currently working on installing the perimeter trench drain for the field.
MUSCO stadium lights have been installed.
Walls 1, 2, and 12 are complete.
Installing walls 13 and 15 currently.
Concession stand concrete walls are installed.
Currently working on the remaining footings of the concession stand.
Continuing to run underground electric throughout the football stadium.