Parking Deck

  • Elevator installed and finished (09.19.2025)

Phase 2-Aux Gym, Auditorium, and Ball Fields

  • Got Elevations for both USG, will be working on bringing it up to grade

  • Continuing with wall / waterproofing / backfilling are G & F

  • Continuing CMU wall / footings

  • Continuing plumbing & electric rough-in

  • Upgraded grandstand footing plan - Footings start week of September 29th.

  • WSSC inspected & passed plumbing